Bankura-Sonamukhi Electrification Work Completed

Electrification work completed in Bankura-Sonamukhi

Electrification work of Bankura-Sonamukhi Section in Adra Division of South Eastern Railway has been completed and Commissioner of Railway Safety will inspect the electrification work on 18th July, 2025 for necessary safety clearance. Bankura- Sonamukhi section is a part of Bankura-Masagram Electrification Project. The total length of the electrification project from Bankura to Masagram is 118 km and the estimated cost is Rs 106.45 crores.

At present, the electrification work of 41 km Bankura-Sonamukhi Section has been completed at a cost of approx Rs. 41.8 crores. There are total 8 Passenger Halts between Bankura and Sonamukhi. The work of the remaining portion of the project between Sonamukhi and Masagram which is of 77 Km is going on in full swing.

The completion of the total electrification work from Bankura to Masagram will help to establish a seamless operation in the section. The electrification work will also ensure better connectivity and punctuality in service by providing energy efficient and pollution free transportation.

Here’s the verified update on the electrification of the Bankura–Sonamukhi railway section, part of the larger Bankura–Masagram electrification project under South Eastern Railway (SER):


✅ Completed: Bankura → Sonamukhi Electrification

  • The 41 km Bankura–Sonamukhi section (of the 118 km Bankura–Masagram line) had its electrification work completed by July 2025, at an approximate cost of ₹41.8 crore
  • The Commissioner of Railway Safety (CRS) inspected the section on 18 July 2025 for approval before electric train services began

🔄 Context: Bankura–Masagram Electrification Project

  • The project aims to electrify the full 118 km stretch between Bankura and Masagram, enhancing connectivity and reducing journey times via the shorter route to Howrah
  • While the Sonamukhi section is done, the remaining 77 km (Sonamukhi → Masagram) remains under active electrification work
  • Once complete, this will allow seamless running of electric services across the full Bankura–Masagram corridor

🗣 On-Ground Community Insight

  • As posted on rail enthusiast forum IndiaRailInfo, the CRS inspection for the Bankura–Sonamukhi section was successfully carried out on 18 July 2025, coinciding with Community posts confirming electrification completion and upcoming MEMU services deployment
  • These anticipations included new MEMU rakes being introduced once the electrified track received clearance

📋 Summary Table

Feature Detail
Route section Bankura → Sonamukhi (41 km)
Project larger scope Bankura → Masagram (118 km total)
Completion date (Sonamukhi) July 2025
CRS safety inspection date 18 July 2025
Cost (Bankura–Sonamukhi) ~₹41.8 crore
Remaining section 77 km (Sonamukhi → Masagram), still under progress
Full corridor aim Seamless electric service to Howrah via Masagram

🚉 What to Expect Next

  • Following CRS approval, MEMU train services were planned to begin using the newly energized section—primarily starting from Bankura with future extensions toward Masagram once full electrification is in place
  • Completion of the Sonamukhi–Masagram section will enable uninterrupted electric operation and improved regional connectivity.

✅ In Summary

  • Electrification of the Bankura–Sonamukhi (41 km) stretch was successfully completed in July 2025, with CRS inspection held on 18 July 2025.
  • The balance 77 km to Masagram is ongoing, and full corridor electrification is expected to enhance services soon.

Would you like updates on service schedules, current MEMU operations, or timeline for electrifying the remaining section to Masagram?