Rail Budget for Uttarakhand 2025- 2025

Allocation of Railway Budget for Uttarakhand for the year 2025-22, for building world-class rail infrastructure.

On Going Railway Projects

Note: Projects falling fully and partly in the state

Here’s a comprehensive breakdown of Uttarakhand’s railway allocation in the Union Budget 2025-26, along with key projects and strategic developments:


Overall Allocation & Historical Context


Major Projects & Infrastructure Highlights

1. New Railway Lines & Project Spending

2. Rishikesh–Karnaprayag Rail Link (Char Dham Project)

3. Kichha–Khatima Line


Electrification, Tracks, and Safety Works


Stations, Passenger Amenities & Vande Bharat


Summary Table

Category Details
Budget (FY 2025-26) ₹4,641 crore
Increase over 2009–14 Avg. Nearly 25×
New Lines Sanctioned 3 lines, 216 km, ₹40,384 crore
Expenditure (Mar 2025) ₹19,898 crore spent; 16 km commissioned
Rishikesh–Karnaprayag Line 125 km; ₹24,659 crore; 199 km tunneling completed
Deoband–Roorkee Line 27 km; completed; significantly cuts travel distance
Kichha–Khatima Line 63 km; ₹228 crore
Track & Electrification (2025–25) 69 km new track; 303 km electrified; 100% electrification
Kavach Safety System Recommended for 49 km
Amrit Stations 11 stations; ₹147 crore
Passenger Facilities 100 flyovers/underbridges; 6 lifts; 14 escalators; Wi-Fi at 31 stations
Vande Bharat Trains 2 units operational

Why This Matters


Need a deep dive into the Char Dham Railway’s completed tunnel segments, project timelines, or specific station upgrades? I’ve got you covered!